P-986, P-987, P-989 Buildings
Yorktown Naval Weapons Station
The project consisted of 3 buildings: the 7,000 SF P-986 Motor Transportation Facility with Humvee washout station and sediment pits; the 30,000 SF P-987 warehouse with loading docks; and the P-989 7,000 SF armory with an 8" topping slab. Bayside Concrete installed the foundations, pedestals, ramps, stairs, loading docks, apron slab, dumpster pads, bollards, interior slab on grade, exterior slab on grade, beams, wash rack, columns, and roof slab on metal deck.
General Contractor
Hourigan Construction
Total Building Area
44,000 SF
Concrete Work Duration
December 2013
Superintendent
Norman Booker