FedEx Freight Service Center

Chesapeake 

This new distribution hub will include 86 bays with over 172 shovel poured bollards. Bayside Concrete installed the footings, foundations, vehicle ramps. loading docks, CIP stairs, patio, stem walls, 42,720 SF warehouse slab on grade, 5,151 SF ofice slab on grade, maintenance building pad, retaining walls, and generator pads.

General Contractor

RRMM Design Build

Total Building Area

47,871 SF

Concrete Work Duration

September 2016

Total Concrete Poured

1,749 cubic yards

Superintendent

Eric Thompson