FedEx Freight Service Center
Chesapeake
This new distribution hub will include 86 bays with over 172 shovel poured bollards. Bayside Concrete installed the footings, foundations, vehicle ramps. loading docks, CIP stairs, patio, stem walls, 42,720 SF warehouse slab on grade, 5,151 SF ofice slab on grade, maintenance building pad, retaining walls, and generator pads.
General Contractor
RRMM Design Build
Total Building Area
47,871 SF
Concrete Work Duration
September 2016
Total Concrete Poured
1,749 cubic yards
Superintendent
Eric Thompson